Add elevator/silver steel colored glaze pan Huaguang, and add new color to the old building.
On the morning of November 25, 2019, the two additional ladders of the Hengyang High-tech Zone Management Committee designed and built by Orrick Elevator were officially put into operation. Stylish and simple modeling, stable and stable comfort, the management committee leaders gave praise and affirmation to this project!
The two additional ladders are in the form of half-story entry, which not only ensures the safety and durability of the elevator, but also minimizes the impact of the surrounding environment, while highlighting the ornamental value of the elevator. The surrounding glass curtain wall is equipped with a panoramic sightseeing elevator, which has become a unique scenery in the office park of the High-tech Zone Management Committee.
This elevator installation project faces many uncertain factors, not only to ensure the smooth progress of the elevator installation project, but also to ensure that the safety of the main structure of the office building and the overall function are not affected, facing many constraints and difficulties.
Orrick Elevator has set up a special working group for installing elevators, taking the needs of the park as the starting point, actively organizing planning and coordinating water, electricity, gas and other related units involved in cutting and reforming, so as to facilitate the construction to the greatest extent. In order to fully improve the conditions for going upstairs and downstairs and continuously improve the construction drawings, the elevator construction scheme was finally determined after many scheme analysis and demonstration meetings.
Time is tight and the task is urgent. Hengyang has been shrouded in cloudy and drizzling rain for several weeks. In order to ensure the completion of the elevator project on schedule with good quality and quantity, members of the Orrick elevator project team have successfully completed the elevator commissioning node target from the aspects of elevator site selection, type selection, demolition and reinforcement, steel structure installation, elevator installation and acceptance, and carefully organized the construction day and night, delivered to the customer a perfect answer sheet.